[Obm] Re: Query on OBM Tool
Pierre Baudracco
pierre.baudracco at aliasource.fr
Tue May 29 15:32:10 CEST 2007
Mahesh Krishnan a écrit :
> I have a query regarding the time sheet ( Production >Time Management tab)
hi,
> 1) Can the task duration be more than 8 hrs , or decimals ( say 1.5 hours )
Not actually
> 2) The date of timesheeet is only from Mon-fri in the demo . Is there
> provision to book for Sat and Sunday in the full installation ?
yes, see these directives (and set them in your obm_conf.inc)
// Time : Worked days in a week (start at sunday)
$c_working_days = array(0,1,1,1,1,1,0);
// Time : Day beginning a week (0=Sunday, 1=Monday,...)
$c_week_first_day = 1;
bye
--
------------------------------------------------------------------------------